To raise a house with your own hands, the step-by-step instructions say the following:
Posted: Mon Feb 17, 2025 9:47 am
House Lifting Instructions
In practice, house raising is carried out quite rarely, but if it is done, then all the work that is possible during this event is done. This includes replacing rotten lower logs, and treating them with chemical compounds against fungus, and a complete repair of the foundation. At the same time, the building frame is leveled.
Logs prepared to replace rotten ones must be dry, physician data by bark beetles and treated with special solutions that protect against moisture. Bricks for the foundation are chosen well-burnt and red. They are suitable for corners, withstand a load of several tons and are not afraid of moisture. It is also necessary to prepare cement and sand for the solution.
All actions to lift the structure are done slowly and strictly observing safety precautions. It is best to start such an event in the morning.
Start with the most sunken corner. At a distance of about a meter from it, dig a hole in the ground to install the jack with the flooring. The soil should be hard and dry.
The lift is placed under the lower log, and if it is intact and strong, a prepared steel plate is placed under the head of the device. If the log is rotten, a recess is cut for the jack pin to a stronger surface.
Proceed directly to lifting the corner. Do it carefully. The height of lifting should not exceed 5-6 cm at a time. At the same time, wedged in the prepared supports and stands to ease the load on the lift.
The structure is carefully examined to identify any unforeseen complications.
If there are two jacks, prepare the second corner for lifting. Also dig a hole for the pallet, on which the next lift is placed. Place it under the log, put a plate on the head and lift the house. Install the prepared bars and planks under the lower crown.
Place the jack in the middle of the log. Do the same operations. Raise it a little, about 2-3 cm. Be sure to put supports under it.
Return to the first corner. Raise, trying to align the frame, but no more than 6-7 cm. Be sure to insert supports from logs or planks. Try to make sure that the entire side is on the supports.
They inspect the structure again.
In practice, house raising is carried out quite rarely, but if it is done, then all the work that is possible during this event is done. This includes replacing rotten lower logs, and treating them with chemical compounds against fungus, and a complete repair of the foundation. At the same time, the building frame is leveled.
Logs prepared to replace rotten ones must be dry, physician data by bark beetles and treated with special solutions that protect against moisture. Bricks for the foundation are chosen well-burnt and red. They are suitable for corners, withstand a load of several tons and are not afraid of moisture. It is also necessary to prepare cement and sand for the solution.
All actions to lift the structure are done slowly and strictly observing safety precautions. It is best to start such an event in the morning.
Start with the most sunken corner. At a distance of about a meter from it, dig a hole in the ground to install the jack with the flooring. The soil should be hard and dry.
The lift is placed under the lower log, and if it is intact and strong, a prepared steel plate is placed under the head of the device. If the log is rotten, a recess is cut for the jack pin to a stronger surface.
Proceed directly to lifting the corner. Do it carefully. The height of lifting should not exceed 5-6 cm at a time. At the same time, wedged in the prepared supports and stands to ease the load on the lift.
The structure is carefully examined to identify any unforeseen complications.
If there are two jacks, prepare the second corner for lifting. Also dig a hole for the pallet, on which the next lift is placed. Place it under the log, put a plate on the head and lift the house. Install the prepared bars and planks under the lower crown.
Place the jack in the middle of the log. Do the same operations. Raise it a little, about 2-3 cm. Be sure to put supports under it.
Return to the first corner. Raise, trying to align the frame, but no more than 6-7 cm. Be sure to insert supports from logs or planks. Try to make sure that the entire side is on the supports.
They inspect the structure again.